Direct lithium extraction from brine · Northeast Texas · Smackover Formation · Illustrative example
9
steps
6
agencies
~20 months
to earliest construction start
Injection wells
critical path
SEQUENCE / CRITICAL PATH
Critical path
Parallel
If applicable
Risk
MONTHS FROM KICKOFF
M0
M4
M8
M12
M16
M20
M24
PREPARE
Earliest construction start · ~M20
Brine rights & leasing
Risk
Reservoir test well & brine data
STATE REVIEW
Brine production project permit
Class V spent-brine injection wells
Risk
Air permit for processing plant
Water supply permit
FEDERAL & LOCAL
Section 404 wetlands permit
If applicable
Construction stormwater authorization
County floodplain & road use permits
WHAT TAVNIT FLAGS
Two agencies, one well
Spent-brine injection wells may need both state and EPA approval. File with both early. This is the critical path.
Settle brine rights first
Texas law on brine ownership and royalties is still evolving. Unclear rights can stall everything downstream.
Run in parallel
Air and water supply permits can advance while reservoir data is still being collected.
ALL REQUIREMENTS
Permit
Agency
Level
Triggered by
Typical duration
Depends on
PRE-PERMIT
Brine rights & leasing
Private landowners
Private
Securing brine ownership, leases, and royalties
6–9 mo
None — begin at kickoff
Reservoir test well & brine data
Railroad Commission of Texas
State
Testing the reservoir and collecting brine data
6–9 mo
Initial brine rights / site access
STATE
Brine production project permit
Railroad Commission of Texas
State
Producing brine to extract minerals
4–6 mo
Reservoir test well & brine data
Class V spent-brine injection wells
Railroad Commission of Texas + EPA Region 6
State
Returning spent brine underground
6–9 mo
Reservoir test well & brine data
Air permit for processing plant
TCEQ
State
Emissions from the processing plant
6–9 mo
Plant design and emissions estimates
Illustrative only. Actual requirements and timelines depend on site conditions and agency review.